I'm on BART a lot from Oakland to the City, etc. With the installation of the new fare gates at West Oakland last December, the effect on the composition of the rider population for the better was obvious immediately. For years before I felt that BART was perhaps the only train/subway in the world making multiple scheduled stops in a loony-bin for pick-ups and drop-offs.


BART has made the historic purchase of brand-new fare gates to be installed systemwide as part of its latest effort to improve the customer experience and overhaul safety in the system. The new fare gates bring a new look and improved experience, offering state-of-the-art technology that will boost safety by reducing fare evasion, enhancing access for people in wheelchairs and those who bring bikes and strollers on BART, and optimizing the reliability and maintenance needs of the fare gates.


View and download the Next Generation Fare Gate Project Fact Sheet.


View and download the latest schedule.


Project timeline: 

The West Oakland pilot gates opened in December 2023.

By the end of February 2025, BART will have completed more than half our 50 stations.

Full deployment systemwide will be completed by the end of 2025.


Completed Stations


  • West Oakland (work started the week of December 11, 2023, and was completed December 28, 2023)
  • Civic Center (platform gate replaced April 2024, work on the concourse gates began in July 2024 and the entire station was completed August 29, 2024) 
  • Fruitvale (work began August 13, 2024, and was completed on August 21, 2024)
  • Richmond (work started the week of September 3, 2024 and was completed on September 13, 2024)
  • Oakland International Airport (work started the week of September 15, 2024 and was completed September 20, 2024)
  • 24th St./Mission (work started the week of September 3, 2024 and was completed September 21, 2024)
  • Antioch (work started the week of September 16 and was completed September 30, 2024)
  • 16th St/Mission (work started October 1, 2024 and was completed October 12 2024)

Work Underway

  • SFO (work began October 11, 2024)

The Next Stations 

  • Montgomery St. (work will begin in Oct 2024)
  • Coliseum (work will begin in Oct 2024)
  • Powell St. (work will begin in Oct 2024)
  • Warm Springs (work will begin in Nov 2024)
  • 12th St/Oakland City Center (work will begin in Nov 2024)
  • Dublin/Pleasanton (work begins in Dec 2024)
  • Pittsburg Center (work begins in Dec 2024)
  • Downtown Berkeley (work begins in Dec 2024)
  • Embarcadero (work begins in Jan 2025)
  • Rockridge (work begins in Jan 2025)
  • Hayward (work begins in Jan 2025)
  • Concord (work begins in Jan 2025)
  • South Hayward (work begins in Jan 2025)
  • Glen Park (work begins in Jan 2025)
  • San Leandro (work begins in Feb 2025) 
  • El Cerrito Plaza (work begins in Feb 2025) 
  •  Lafayette (work begins in Feb 2025) 
  • Orinda (work begins in Feb 2025) 


New Fare Gates & Station Hardening